Overview

Muara Tawar Block 2,3,4 Add-On   Muara Tawar Power Plant plays a very important role in supporting the reliability of Jakarta electricity system. There are 5 (five) blocks of Gas Turbine Power Plant. Block 1 and 5 are already Combined Cycle while the rest is remain Simple Cycle.

To reduce the cost of production and improve the reliability of the system, PLN decided to convert Block 2,3 and 4 into Combined Cycle which will provide additional 650 MW to the grid.

Client

 
PT PLN (Persero) and PT Pembangkitan Jawa Bali  

Location

 

Services

West Java   reCOnsult was appointed as Owner’s Engineer with the wide range of services including:
  • Feasibility Study
  • Bid Document Preparation
  • Engineering/Design Supervision
  • QA/QC Inspection
  • Construction Supervision
  • Project Management

Expertise

 
Owner's Engineer  

Years

 
2013 - now